Client: FCE Projects

Location: Cowley Hill (Former Pilkington Glass)


Product Description: FCE Projects had constructed a new 33Kv Primary Sub-Station for SP Energy Networks for a future 1100 housing development at the former Pilkington Glass site in St Helens. We were commissioned to carry out all external works including the security fencing and gates.


Scope of works:

  • Install 100m of Palisade fencing 2400mm high, “W” section fencing pales at 3mm thickness and TRI-POINT style, with continuation anti dig ground beam.

  • Provision and placement of 5m x 2.4m High “W” section Vehicle Gates including 3mm Pales.

  • Installation of customer ducts.

  • Installation of complete surface water system to include all building and highway drainage.

  • Installation of Clearwater Full Retention Separator.

  • Full road construction including all kerbing and sub-structure works.

  • Installation of slabbed sub-station access pathway.

  • Provision of 2m wide service strip including PPC edging kerbs, MOT sub-base and 20mm decorative stone.

  • All setting out and levels undertaken in house. 